File #: RES-03:667    Version: 1 Name: Change order with Meadows Construction for Matthews Avenue MATA project
Type: Resolution Status: Passed
File created: 9/18/2003 In control: Public Works Council Committee
On agenda: Final action: 10/6/2003
Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF JONESBORO, ARKANSAS, APPROVING A CHANGE ORDER AND ALLOCATING FUNDS FOR THE MATA MATTHEWS AVENUE CONSTRUCTION II PROJECT
Indexes: Change Order, MATA, Project
Related files: MIN-03:180

title

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF JONESBORO, ARKANSAS, APPROVING A CHANGE ORDER AND ALLOCATING FUNDS FOR THE MATA MATTHEWS AVENUE CONSTRUCTION II PROJECT

body

BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF JONESBORO, ARKANSAS THAT:

 

1.                     A change order in the amount of $94,636 is hereby approved to the existing contract with Meadows Construction Company, Inc.  for the completion of the MATA Matthews Avenue Construction II Project

 

2.                     The sum of $11,330 is to be provided from allocated MATA funds

 

3.                     The sum of $49,363 is allocated from funds appropriated in the 2003 City budget, Account Number 13-100-152-00, for drainage improvements near the First Baptist Church

 

4.                     The sum of $33,943 is allocated from funds appropriated in the 2003 City budget, Account Number 13-100-152-00, for drainage improvements near the First United Methodist Church.

 

5.                     This resolution shall take effect immediately.

 

PASSED AND ADOPTED THIS 6th day of October, 2003.