File #: CON-253    Version: 1 Name: Stonebridge Construction, LLC. contract for the construction of the Union Street and Cate Street Parking Improvement project
Type: Contract Status: Passed
File created: 8/5/2008 In control: Public Safety Council Committee
On agenda: Final action: 4/1/2009
Title: Stonebridge Construction, LLC. contract for the construction of the Union Street and Cate Street Parking Improvement project
Sponsors: Engineering
Indexes: Contract
Attachments: 1. RES-08:116, 2. Contract, 3. Change Order No. 1, 4. Change Order No. 2, 5. Change Order No. 3, 6. Change Order No. 4, 7. Change Order No. 5, 8. Change Order No. 6, 9. Change Order No. 7, 10. Change Order No. 8, 11. Change Order No. 9
Related files: RES-08:116
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Stonebridge Construction, LLC. contract for the construction of the Union Street and Cate Street Parking Improvement project
body
Stonebridge Construction, LLC. was awarded the contract for the construction of the Union Street & Cate Street Parking Improvement project and was signed on August 11, 2008. The contract amount is for $329,552.69 and the work should be completed within 90 days after the Notice to Proceed has been issued. The resolution number is RES-08:116 and was approved by the City Council on August 5, 2008.

The contract was amended by Change Order No. 1 to include the installation of an underground electrical meter for Abilities Unlimited (Materials provided by CWL). The change order amount is $600 and was signed on September 19, 2008.

The contract was amended a second time by Change Order No. 2 to include curb and gutter replacement and additional undercut and backfill for the Union Street Parking Improvement project. The change order was signed on November 6, 2008 and the amount is for $3,239.11.

The contract was amended a third time by Change Order No. 3 to include tank removal and additional aggregate base for the Cate Street Parking Improvement project. The change order was signed on November 6, 2008 and the amount is for $2,071.95.

The contract was amended a fourth time by Change Order No. 4 to increase the contract time for the Union Street Parking Improvement project. The length of the contract was increased an extra 32 days and was signed on December 6, 2008.

The contract was amended a fifth time by Change Order No. 5 to increase the contract time for the Cate Street Parking Improvement project. The length of the contract was increased an extra 32 days and the change order was signed on December 8, 2008.

The contract was amended a sixth time by Change Order No. 6 to include additional asphalt concrete hot mix surface mix on Madison Street, additional aggregate base course on Madison Street, additional unclassified excav...