Bailey Contractors, Inc. contract for the construction on the Fueling Depot Facility
body
Bailey Contractors, Inc. entered into a contract with the City of Jonesboro for the construction of the Fueling Depot Facility. The contract amount is $686,226.00 and the work is to be completed within 18 calendar weeks from the date of commencement. The resolution number is RES-11:119 and was approved by Council on July 19, 2011.
The contract was amended by Change Order No. 1 to include various items listed on change order. The new contract amount is $640,226.00 and was signed on August 3, 2011.
Attachments included are:
RES-11:119
Contract
Change Order No. 1