Gillis Farms was awarded the contract for the construction of the Valley & Owens drainage improvements and was signed on August 9, 2007. The contract amount is for $396,482 and the work is to be completed within 120 days. The resolution number is RES-07:643 and was approved by the City Council on August 7, 2007.
The contract amount was amended by Change Order #1 to $402,682.
The contract amount was amended again by Change Order #2 to $403,991. T
he work completion date was amended again by Change Order #3 to 150 days.