File #: CON-260    Version: 1 Name: Tridant Builders, Inc. contract for the construction of the Turtle Creek Greenway Phase 1 - Pedestrian Bridge - Job No. 2009:33
Type: Contract Status: Passed
File created: 2/2/2010 In control: Public Works Council Committee
On agenda: Final action: 5/4/2010
Title: Tridant Builders, Inc. contract for the construction of the Turtle Creek Greenway Phase 1 - Pedestrian Bridge - Job No. 2009:33
Sponsors: Engineering
Indexes: Contract
Attachments: 1. RES-09:208, 2. Contract, 3. RES-10:051, 4. Change Order No. 1
Related files: RES-10:051, RES-09:208
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Tridant Builders, Inc. contract for the construction of the Turtle Creek Greenway Phase 1 - Pedestrian Bridge - Job No. 2009:33
body
Tridant Builders, Inc. was awarded the contract for the construction of the Turtle Creek Greenway Phase 1 - Pedestrian Bridge - Job No. 2009:33 and was signed on February 2, 2010. The contract amount is for $178,000 and the work should be completed within 150 days after the Notice to Proceed has been issued. The resolution number is RES-09:208 and was approved by the City Council on February 2, 2010. The contract amount was amended by Change Order No.1 to allow for dredging of the retention pond. The contract amount is for an additional $19,600. The resolution number is RES-10:051 and was approved by the City Council on May 4, 2010.
 
Attachments included are:
 
RES-09:208
Contract
 
RES-10:051
Change Order No. 1