Cameron Construction Company was awarded the contract for the CDBG-R North Jonesboro sidewalk improvements project for Job No. 2009:44. The contract amount is for $138,380 and the work is to be completed within 180 days. The resolution number is RES-09:195 and was approved by the City Council on December 15, 2009. The contract amount was increased to $147,557.00 and length of the contract was increased to 233 days by Change Order No. 1. The new contract amount was decreased to $146,703 and the length of the contract was decreased to 222 days by Change Order No. 2.