Cameron Construction Company contract for the construction of the Washington Avenue and Bridge Street intersection improvement project
body
Cameron Construction Company was awarded the contract for the construction of the Washington Avenue & Bridge Street intersection improvement project and was signed on November 26, 2008. The contract amount is for $234,501.00 and the work is to be completed within 60 days. The resolution number is RES-08:203 and was approved by the City Council on November 18, 2008.
The first change order changed the amount to $234,488.40.
The second change order changed the amount to $234,738.40 and the work is to be completed within 74 days.
The third change order changed the amount to $229,706.40 and the work is to be completed within 73 days.