File #: CON-063    Version: 1 Name: Cameron Construction Company contract for the construction of the Race Street & Fair Park Boulevard intersection improvement project
Type: Contract Status: Passed
File created: 9/16/2008 In control: Public Works Council Committee
On agenda: Final action: 6/23/2009
Title: Cameron Construction Company contract for the construction of the Race Street & Fair Park Boulevard intersection improvement project
Sponsors: Engineering
Indexes: Contract
Attachments: 1. RES-08:162, 2. Contract, 3. RES-08:075, 4. Change order #1, 5. Change order #2, 6. Change order #3
Related files: RES-08:162, ORD-08:075
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Cameron Construction Company contract for the construction of the Race Street & Fair Park Boulevard intersection improvement project
body
Cameron Construction Company was awarded the contract for the construction of the Race Street & Fair Park Boulevard intersection improvement project and was signed on September 18, 2008. The contract amount is for $188,126.00 and the work is to be completed within 60 days. The resolution number is RES-08:162 and was approved by the City Council on September 16, 2008.
 
The contract amount was amended by Change Order No. 1 to $188,125.92 and was signed on October 15, 2008.
 
The contract amount was amended a second time by Change Order No. 2 to $190,975.92 and was signed on June 10, 2009.
 
The contract amount was changed to $189,651.52 and the completion date was changed to 152 days by Change Order No. 3 and was signed on June 23, 2009.
 
Attachments included are:
 
RES-08:162
Contract
ORD-08:075
Change Order #1
Change Order #2
Change Order #3