File #: CON-191    Version: 1 Name: Miller Newell Engineers contract for the Farm Creek Detention pond drainage project
Type: Contract Status: Passed
File created: 8/15/2006 In control: Public Works Council Committee
On agenda: Final action: 9/5/2006
Title: Miller Newell Engineers contract for the Farm Creek Detention pond drainage project
Sponsors: Engineering
Indexes: Contract
Attachments: 1. Resolution 2006:105, 2. Contract for the Preliminary Engineering, 3. Resolution 2006:122, 4. Contract for the construction of Storm Drainage Improvements
Related files: RES-06:257, RES-06:239
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Miller Newell Engineers contract for the Farm Creek Detention pond drainage project
body
Miller Newell Engineers was awarded the contract for the preliminary engineering of the Farm Creek detention pond drainage project. The contract amount is for $4,000 and the work shall be completed by September 5, 2006. The resolution number 2006:105 and was approved by the City Council on August 15, 2006.
 
They were also awarded the contract for construction of Storm Drainage Improvements in the Farm Creek Drainage Basin. The contract amount is for $20,600. The resolution number is 2006:122 and was approved by the City Council on September 5, 2006.
 
Attachments included are:
 
Resolution 2006:105
Contract for the preliminary engineering
 
Resolution 2006:122
Contract for the construction of Storm Drainage Improvements