B.B. Vance renovations for the Justice Complex contract
body
B.B. Vance was awarded the contract to provide renovations to the Justice Complex located at 410 West Washington Avenue. The contract amount is for $130,594 and was signed on March 22, 2006. Work is to be completed by May 1, 2006. The ordinance number is 3624 and was approved by the City Council on March 21, 2006.
Attachments included are:
Ordinance
Contract
Bid sheet
Letters from various companies concerning the trusses