File #: RES-10:048    Version: 1 Name: Change Order with Cameron Construction for Nettleton Avenue Drainage Improvements
Type: Resolution Status: Passed
File created: 4/22/2010 In control: Public Works Council Committee
On agenda: Final action: 5/18/2010
Title: A RESOLUTION TO THE CITY OF JONESBORO, ARKANSAS TO APPROVE A CHANGE ORDER WITH CAMERON CONSTRUCTION COMPANY, INC. FOR NETTLETON AVENUE DRAINAGE IMPROVEMENTS - 2009:30
Sponsors: Engineering
Indexes: Change Order, Contract
Attachments: 1. Change Order #1
Related files: RES-09:115, CON-060

Title

A RESOLUTION TO THE CITY OF JONESBORO, ARKANSAS TO APPROVE A CHANGE ORDER WITH CAMERON CONSTRUCTION COMPANY, INC. FOR NETTLETON AVENUE DRAINAGE IMPROVEMENTS - 2009:30

Body

WHEREAS, the City of Jonesboro desires to change the Nettleton Avenue Drainage Improvements project with Change Order No. 1 as attached increasing the contract $28,396.50, the new contract amount is $470,447.00; and

 

WHEREAS, the funding for the Change Order shall come from the 2010 Capital Improvements budget and compensation shall be paid in accordance with the contract documents for this project.

 

NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL FOR THE CITY OF JONESBORO, ARKANSAS THAT:

 

Section 1. The City of Jonesboro shall accept Change Order No. 1 in the amount of $28,396.50 from Cameron Construction Company, Inc. for the Nettleton Avenue Drainage Improvements project.

 

Section 2. Funding for the Change Order shall come from the 2010 Capital Improvements budget and compensation shall be paid in accordance with the contract documents for this project.

 

Section 3. The Mayor and City Clerk are hereby authorized by the City Council for the City of Jonesboro to execute all documents necessary to effectuate this change order.

 

PASSED AND APPROVED this 18th day of May, 2010.