Construction Network was awarded the contract for the construction of Fire Stations #2 and #6. The contract amount is for $3,889,000 and the work has to be completed within 240 days from the date of commencement of work. The resolution number is RES-08:112 and was approved by the City Council on July 15, 2008.
The contract amount was amended by Change Order #1 to $2,081,357.
The contract amount was amended again by Change Order #2 to $4,057,075.87 and the date of completion was extended 10 days. RES-09:055 authorized Change Order #2 and was approved by the City Council on May 5, 2009.
Construction Network, Inc. was award the contract for the construction of Fire Station #4. The contract amount is for $1,684,900 and the work should be completed within 240 consecutive calendar days from the date of commencement. The resolution number is RES-11:096 and was approved by Council on June 7, 2011.
Attachments included are:
Res-08:112
Contract
Change Order #1
RES-09:055
Change Order #2
RES-11:096
Contract for Fire Station #4