File #: CON-370    Version: 1 Name: Bailey Contractors, Inc. contract for the construction of the vehicle maintenance facility - JOB No. 2010:23
Type: Contract Status: Passed
File created: 10/7/2010 In control: City Council
On agenda: Final action: 8/3/2011
Title: Bailey Contractors, Inc. contract for the construction of the vehicle maintenance facility - JOB No. 2010:23
Indexes: Contract
Attachments: 1. RES-10:125, 2. Contract, 3. RES-10:141, 4. Change Order No. 1, 5. Change Order No. 2, 6. Change Order No. 3, 7. Change Order No. 4, 8. Change Order No. 5
Related files: RES-10:125, RES-10:141
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Bailey Contractors, Inc. contract for the construction of the vehicle maintenance facility - JOB No. 2010:23
body
Bailey Contractors, Inc. was awarded the contract for the construction of the vehicle maintenance facility - JOB No. 2010:23 and was signed on September 22, 2010. The contract amount is for $1,445,000.00 and the project should be completed no later than 266 days from the date of commencement. The resolution number is RES-10:125 and was approved by the City Council on September 27, 2010.
 
The contract was amended to include changes to the slab and the amount was increased to $1,464,408.60 by Change Order No. 1. The resolution number is RES-10:141 and was approved by Council on November 16, 2010.
 
The contract was amended a second time to include changes to the pressure washer piping and the amount was increased to $1,465,516.98 by Change Order No. 2. The change order was signed on December 27, 2010.
 
The contract was amended a third time to changes to the ridge line of two walls and the amount was increased to $1,468,472.66 by Change Order No. 3. The change order was signed on February 1, 2011.
 
The contract was amended a fourth time for various items and the amount was increased to $1,478,288.65 and was signed on June 3, 2011.
 
The contract was amended a fifth time to change two wash sinks out & install drinking fountains and the amount was increased to $1,480,361.04. The change order was signed on August 3, 2011.
 